Sync 2.0 Sprint 1 Announcement

Hi Everyone,

In the first sprint, we’ll prepare base for AtomFeed, Sync 2.0 and FHIR module. For code quality, we’ll add tools like pmd, checkstyle and findbugs. Next, our work will be focused on the Atom Feed module. Specifically, we’ll change advice based feed propagation to event-based, atom feed configuration will be stored as JSON file.

Objectives:

  • Prepare the base for FHIR, AtomFeed and Sync 2.0 module.
  • Code quality
  • Change feed propagation to event-based
  • Move AtomFeed configuration to file.

Start Date: 17/10/2017 End Date: 31/10/2017

JIRA Board: https://issues.openmrs.org/secure/RapidBoard.jspa?rapidView=121 On next week we’ll announce the date of the first sprint demo.