Hi Everyone,
The thread for weekly reports. Every working week will end with summarizing our team efforts.
Regards, Przemyslaw
Hi Everyone,
The thread for weekly reports. Every working week will end with summarizing our team efforts.
Regards, Przemyslaw
Weekly progress report.
SolDevelo Sp. z o.o. Mail - OpenMRS - SYNC 2.0 18.10.2017-24.10.pdf (165.4 KB)
Edit:
Report for: 2017-10-18 - 2017-10-24
Sprint: Sprint 1, 2017-10-17 - 2017-10-31
Sprint Goals:
Period value:
'%' closed tickets with high priority: 0% (0/0)
'%' closed tickets with medium priority: 80% (12/15)
'%' closed tickets with low priority: 0% (0/0)
'%' completed: 80% (12/15)
Worked hours by team member (worked/expected):
PM:
Przemysław Kornowski - 40.0/40.0
Dev:
Arkadiusz Lalo - 22.0/24.0
Daniel Serkowski - 18.5/24.0
What's done:
Ticket | Estimation(h) | Worked(h) | Total Worked(h) | Priority | Responsible |
---|---|---|---|---|---|
SYNCT-8: Add default configuration file. | 3.0 | 2.0 | 2.0 | TBD | Arkadiusz Lalo |
SYNCT-7: Add Travis CI to Sync 2.0 | 6.0 | 1.0 | 1.0 | TBD | Przemysław Kornowski |
SYNCT-2: Add to Sync 2.0 code quality tools | 5.0 | 0.5 | 4.5 | TBD | Arkadiusz Lalo |
SYNCT-1: Create the Sync2 module from template | 5.0 | 0.5 | 4.5 | TBD | Arkadiusz Lalo |
ATF-10: Add code quality tools to AtomFeed module | 5.0 | 0.5 | 5.0 | TBD | Daniel Serkowski |
FM-203: Add code quality tools to FHIR module | 12.0 | 0.0 | 8.0 | TBD | Przemysław Kornowski |
ATF-5: Default configuration for OpenMRS feed | 2.0 | 2.0 | 2.0 | TBD | Przemysław Kornowski |
ATF-4: Create the feed config class | 3.0 | 0.5 | 3.0 | TBD | Daniel Serkowski |
ATF-11: Add Travis CI to Atomfeed | 6.0 | 2.0 | 2.0 | TBD | Przemysław Kornowski |
ATF-1: Create the Atom Feed module from template | 5.0 | 0.5 | 5.0 | TBD | Daniel Serkowski |
FM-202: Clean up FHIR strategy code | 12.0 | 11.5 | 11.5 | TBD | Przemysław Kornowski |
ATF-2: Switch the advice based feed propagation to event based | 16.0 | 19.5 | 19.5 | TBD | Daniel Serkowski |
Total | 80.0 | 40.5 | 68.0 |
What's in progress:
Ticket | Estimation(h) | Worked(h) | Total Worked(h) | Remaining(h) | Priority | Responsible |
---|---|---|---|---|---|---|
SYNCT-9: Create config classes | 6.0 | 1.0 | 1.0 | 5.0 | TBD | Arkadiusz Lalo |
ATF-6: Create config parser and manager | 24.0 | 19.0 | 19.0 | 5.0 | TBD | Arkadiusz Lalo |
ATF-7: Feed config UI | 20.0 | 19.5 | 19.5 | 0.5 | TBD | Przemysław Kornowski |
Total | 50.0 | 39.5 | 39.5 | 10.5 |
Invalid tickets:
Ticket | Estimation(h) | Worked(h) | Total Worked(h) | Priority | Responsible |
---|---|---|---|---|---|
SYNCT-4: Add configuration variables for Sync 2.0 | 8.0 | 0.5 | 0.5 | TBD | Arkadiusz Lalo |
@pkornowski Will it be possible to write the weekly reports directly in this thread instead of attaching them?
@jslawinski I think it is possible. I’ll do that.
Report for: 2017-10-24 - 2017-10-30
Sprint: Sprint 1, 2017-10-17 - 2017-10-31
Sprint goals:
Period value:
'%' closed tickets with high priority: 0% (0/0)
'%' closed tickets with medium priority: 70% (7/10)
'%' closed tickets with low priority: 0% (0/0)
'%' completed: 70% (7/10)
Worked hours by team member (worked/expected):
PM:
Przemysław Kornowski - 37.5/40.0
Dev:
Arkadiusz Lalo - 22.0/24.0
Daniel Serkowski - 26.5/24.0
What's done:
Ticket | Estimation(h) | Worked(h) | Total Worked(h) | Priority | Responsible |
---|---|---|---|---|---|
SYNCT-10: Create config service for Sync 2.0. | 6.0 | 7.0 | 7.0 | TBD | Arkadiusz Lalo |
SYNCT-9: Create config classes | 6.0 | 3.5 | 3.5 | TBD | Arkadiusz Lalo |
SYNCT-8: Add default configuration file. | 3.0 | 2.0 | 2.0 | TBD | Arkadiusz Lalo |
SYNCT-4: Add configuration variables for Sync 2.0 | 8.0 | 0.5 | 0.5 | TBD | Arkadiusz Lalo |
FM-202: Clean up FHIR strategy code | 12.0 | 0.0 | 11.5 | TBD | Przemysław Kornowski |
ATF-2: Switch the advice based feed propagation to event based | 16.0 | 5.5 | 19.5 | TBD | Daniel Serkowski |
ATF-6: Create config parser and manager | 24.0 | 8.5 | 23.0 | TBD | Arkadiusz Lalo |
Total | 75.0 | 27.0 | 67.0 |
What's in progress:
Ticket | Estimation(h) | Worked(h) | Total Worked(h) | Remaining(h) | Priority | Responsible |
---|---|---|---|---|---|---|
SYNCT-5: Add Configuration UI for Sync 2.0 | 24.0 | 6.0 | 6.0 | 18.0 | TBD | Arkadiusz Lalo |
ATF-12: Add Atomfeed server rest api endpoints | 8.0 | 6.0 | 6.0 | 2.0 | TBD | Przemysław Kornowski |
ATF-9: Create AtomFeed server database | 12.0 | 19.0 | 19.0 | 6.0 | TBD | Daniel Serkowski |
ATF-7: Feed config UI | 20.0 | 28.0 | 42.5 | 0 | TBD | Przemyslaw Kornowski |
Total | 64 | 59.0 | 73.5 | 26.0 |
Report for: 2017-10-31 - 2017-11-06
Sprint: Sync 2.0 Sprint 2, 2017-10-31 - 2017-11-14
Period value:
'%' closed tickets with high priority: 0% (0/0)
'%' closed tickets with medium priority: 57% (4/7)
'%' closed tickets with low priority: 0% (0/0)
'%' completed: 57% (4/7)
Worked hours by team member (worked/expected):
PM:
Przemysław Kornowski - 31.0/40.0
Dev:
Arkadiusz Lalo - 19.0/24.0
Daniel Serkowski - 13.0/24.0
What's done:
Ticket | Estimation(h) | Worked(h) | Total Worked(h) | Priority | Responsible |
---|---|---|---|---|---|
SYNCT-12: Backlog Refinement | 16.0 | 15.5 | 15.5 | TBD | Przemysław Kornowski |
SYNCT-5: Add Configuration UI for Sync 2.0 | 24.0 | 15.0 | 21.0 | TBD | Arkadiusz Lalo |
ATF-7: Feed config UI | 20.0 | 1.0 | 43.5 | TBD | Przemysław Kornowski |
FM-217: Create FHIR Strategy for Person object. | 8.0 | 5.0 | 5.0 | TBD | Przemysław Kornowski |
Total | 68.0 | 36.5 | 85.0 |
What's in progress:
Ticket | Estimation(h) | Worked(h) | Total Worked(h) | Remaining(h) | Priority | Responsible |
---|---|---|---|---|---|---|
ATF-12: Add Atomfeed server rest api endpoints | 8.0 | 0.0 | 6.0 | 2.0 | TBD | Przemysław Kornowski |
ATF-9: Create AtomFeed server database | 12.0 | 10.0 | 29.0 | 6.0 | TBD | Daniel Serkowski |
FM-205: Create FHIR Strategy for Patient object. | 8.0 | 0.5 | 0.5 | 7.5 | TBD | Przemysław Kornowski |
Total | 28.0 | 10.5 | 35.5 | 15.5 |
Backlog:
Ticket | Estimation(h) | Worked(h) | Total Worked(h) | Remaining(h) | Status | Priority | Responsible |
---|---|---|---|---|---|---|---|
SYNCT-13: Sprint 1 Review | 10.0 | 10.0 | 10.0 | 0.0 | Closed | TBD | Przemysław Kornowski |
SYNCT-11: Retrospective & Planning 31.10.2017 | 6.0 | 6.0 | 6.0 | 0.0 | Closed | TBD | Arkadiusz Lalo |
Total | 16.0 | 16.0 | 16.0 | 0.0 |
Report for: 2017-11-07 - 2017-11-13
Hours:
Worked (PM/Dev): 97.5 (39.0/58.5)
Total worked hours by team member:
Arkadiusz Lalo - 24.0
Daniel Serkowski - 26.5
Przemysław Kornowski - 39.0
Jakub Trzebiatowski - 4.0
Karol Cissewski - 4.0
Report for: 2017-11-07 - 2017-11-13
Sprint: Sync 2.0 Sprint 2, 2017-10-31 - 2017-11-14
Period value:
'%' closed tickets with high priority: 0% (0/0)
'%' closed tickets with medium priority: 24% (4/17)
'%' closed tickets with low priority: 0% (0/0)
'%' completed: 24% (4/17)
Ticket | Estimation(h) | Worked(h) | Total Worked(h) | Priority | Responsible |
---|---|---|---|---|---|
ATF-12: Add Atomfeed server rest api endpoints | 8.0 | 2.5 | 8.5 | TBD | Przemysław Kornowski |
ATF-9: Create AtomFeed server database & implement logic that write events to the database | 12.0 | 9.0 | 38.0 | TBD | Daniel Serkowski |
FM-213: Create FHIR Strategy for Location object. | 8.0 | 8.0 | 8.0 | TBD | Arkadiusz Lalo |
FM-205: Create FHIR Strategy for Patient object. | 8.0 | 9.0 | 9.5 | TBD | Przemysław Kornowski |
Total | 36.0 | 28.5 | 64.0 |
What's in progress:
Ticket | Estimation(h) | Worked(h) | Total Worked(h) | Remaining(h) | Priority | Responsible |
---|---|---|---|---|---|---|
FM-209: Create FHIR Strategy for Provider object. | 8.0 | 15.5 | 15.5 | 0.0 | TBD | Arkadiusz Lalo |
FM-206: Create FHIR Strategy for Obs object. | 8.0 | 1.0 | 1.0 | 7.0 | TBD | Arkadiusz Lalo |
FM-207: Create FHIR Strategy for Encounter object. | 8.0 | 15.0 | 15.0 | 3.0 | TBD | Przemysław Kornowski |
SYNCT-34: Create the AtomFeed Reader | 32.0 | 19.0 | 19.0 | 13.0 | TBD | Daniel Serkowski |
Total | 56.0 | 50.5 | 50.5 | 23.0 |
What's next:
Ticket | Estimation(h) | Worked(h) | Total Worked(h) | Remaining(h) | Priority |
---|---|---|---|---|---|
FM-214: Create FHIR Strategy for Order object. | 12.0 | 0.0 | 0.0 | 12.0 | TBD |
FM-212: Create FHIR Strategy for Form object. | 8.0 | 0.0 | 0.0 | 8.0 | TBD |
FM-204: Create FHIR Strategy for every object. | 0.0 | 0.0 | 0.0 | 0.0 | TBD |
FM-208: Create FHIR Strategy for Visit object. | 12.0 | 0.0 | 0.0 | 12.0 | TBD |
FM-215: Create FHIR Strategy for Patient Program object. | 8.0 | 0.0 | 0.0 | 8.0 | TBD |
FM-216: Create FHIR Strategy for PatientState object. | 8.0 | 0.0 | 0.0 | 8.0 | TBD |
FM-210: Create FHIR Strategy for Allergy object. | 8.0 | 0.0 | 0.0 | 8.0 | TBD |
FM-219: Create FHIR Strategy for Cohort object. | 8.0 | 0.0 | 0.0 | 8.0 | TBD |
FM-218: Create FHIR Strategy for Relationship object. | 8.0 | 0.0 | 0.0 | 8.0 | TBD |
Total | 72.0 | 0.0 | 0.0 | 72.0 |
Ticket | Estimation(h) | Worked(h) | Total Worked(h) | Remaining(h) | Status | Priority | Responsible |
---|---|---|---|---|---|---|---|
SYNCT-39: Familiarizing with the project | 4.0 | 4.0 | 4.0 | 4.0 | Needs Assessment | TBD | Jakub Trzebiatowski |
SYNCT-38: Familiarizing with the project | 4.0 | 4.0 | 4.0 | 4.0 | Needs Assessment | TBD | Karol Cissewski |
SYNCT-36: Familiarizing with the project | 9.0 | 1.0 | 1.0 | 8.0 | In Progress | TBD | Przemysław Kornowski |
SYNCT-35: Research for supporting older OpenMRS version than 2.0 | 10.0 | 9.5 | 9.5 | 0.5 | Closed | TBD | Przemysław Kornowski |
Total | 27.0 | 18.5 | 18.5 | 16.5 |
Hi everyone,
there is weekly report for period 2017-11-14 - 2017-11-20
Hours:
Worked (PM/Dev): 114.0 (40.0/74.0)
Total worked hours by team member:
Arkadiusz Lalo - 13.0
Daniel Serkowski - 13.0
Jakub Trzebiatowski - 22.0
Karol Cissewski - 26.0
Przemysław Kornowski - 40.0
Report for: 2017-11-14 - 2017-11-20
Sprint: Sync 2.0 Sprint 3, 2017-11-14 - 2017-11-28
Long-term goals:
Period value:
‘%’ closed tickets with high priority: 0% (0/0)
‘%’ closed tickets with medium priority: 17% (4/23)
‘%’ closed tickets with low priority: 0% (0/0)
‘%’ completed: 17% (4/23)
Hours:
Worked (PM/Dev): 96.0 (37.0/59.0)
Remaining: 116.5
Worked hours by team member (worked/expected):
PM:
Przemysław Kornowski - 37.0/40.0
Dev:
Arkadiusz Lalo - 9.0/24.0
Daniel Serkowski - 11.0/24.0
Jakub Trzebiatowski - 15.0/24.0
Karol Cissewski - 24.0/24.0
Ticket | Estimation(h) | Worked(h) | Total Worked(h) | Priority | Responsible |
---|---|---|---|---|---|
SYNCT-41: Sprint 3 Planning 14.11.2017 | 5.0 | 1.0 | 5.0 | TBD | Arkadiusz Lalo |
ATF-19: Current configuration view. | 8.0 | 6.0 | 6.0 | TBD | Jakub Trzebiatowski |
SYNCT-46: Create the Rest Client | 16.0 | 16.0 | 16.0 | TBD | Jakub Trzebiatowski |
SYNCT-43: SyncResourceManager: Method for pull object | 24.0 | 16.0 | 16.0 | TBD | Karol Cissewski |
Total | 53.0 | 39.0 | 43.0 |
What's in progress:
Ticket | Estimation(h) | Worked(h) | Total Worked(h) | Remaining(h) | Priority | Responsible |
---|---|---|---|---|---|---|
SYNCT-34: Create the AtomFeed Reader | 32.0 | 11.0 | 30.0 | 2.0 | TBD | Daniel Serkowski |
FM-209: Create FHIR Strategy for Provider object. | 8.0 | 0.0 | 15.5 | 0.0 | TBD | Arkadiusz Lalo |
FM-206: Create FHIR Strategy for Obs object. | 8.0 | 5.0 | 10.0 | 0.0 | TBD | Karol Cissewski |
FM-207: Create FHIR Strategy for Encounter object. | 8.0 | 2.0 | 17.0 | 1.0 | TBD | Przemysław Kornowski |
FM-239: Create the FHIR Client | 16.0 | 33.5 | 33.5 | 3.0 | TBD | Przemysław Kornowski |
SYNCT-45: Add Rest Client Factory | 8.0 | 0.5 | 0.5 | 7.5 | TBD | Karol Cissewski |
SYNCT-44: SyncResourceManager: Method for persist object | 24.0 | 7.0 | 7.0 | 17.0 | TBD | Arkadiusz Lalo |
Total | 104.0 | 59.0 | 113.5 | 30.5 |
What's next:
Ticket | Estimation(h) | Worked(h) | Total Worked(h) | Remaining(h) | Priority |
---|---|---|---|---|---|
FM-214: Create FHIR Strategy for Order object. | 12.0 | 0.0 | 0.0 | 12.0 | TBD |
FM-212: Create FHIR Strategy for Form object. | 8.0 | 0.0 | 0.0 | 8.0 | TBD |
FM-204: Create FHIR Strategy for every object. | 0.0 | 0.0 | 0.0 | 0.0 | TBD |
FM-208: Create FHIR Strategy for Visit object. | 12.0 | 0.0 | 0.0 | 12.0 | TBD |
FM-215: Create FHIR Strategy for Patient Program object. | 8.0 | 0.0 | 0.0 | 8.0 | TBD |
FM-216: Create FHIR Strategy for PatientState object. | 8.0 | 0.0 | 0.0 | 8.0 | TBD |
FM-210: Create FHIR Strategy for Allergy object. | 8.0 | 0.0 | 0.0 | 8.0 | TBD |
FM-219: Create FHIR Strategy for Cohort object. | 8.0 | 0.0 | 0.0 | 8.0 | TBD |
SYNCT-42: Pull Service: Read AtomFeed | 6.0 | 0.0 | 0.0 | 6.0 | TBD |
ATF-15: Create the atomFeed reader Factory | 8.0 | 0.0 | 0.0 | 8.0 | TBD |
SYNCT-40: Create the service for Pull logic. | 0.0 | 0.0 | 0.0 | 0.0 | TBD |
FM-240: Add FHIR client factory | 8.0 | 0.0 | 0.0 | 8.0 | TBD |
Total | 86.0 | 0.0 | 0.0 | 86.0 |
Ticket | Estimation(h) | Worked(h) | Total Worked(h) | Remaining(h) | Status | Priority | Responsible |
---|---|---|---|---|---|---|---|
SYNCT-37: Sprint 2 Review 14.11.2017 | 8.0 | 8.0 | 8.0 | 0.0 | Closed | TBD | Arkadiusz Lalo |
Report for: 2017-11-28 - 2017-12-04
Sprint: Sync 2.0 Sprint 4, 2017-11-28 - 2017-12-12
Sprint goals:
Audit logic and UI. Start Push Workflow implementation.
Period value:
'%' closed tickets with high priority: 0% (0/0)
'%' closed tickets with medium priority: 24% (5/21)
'%' closed tickets with low priority: 0% (0/0)
'%' completed: 24% (5/21)
Hours:
Worked (Team Leader/Developer): 85.5 (32.0/53.5)
Remaining: 126.0
Worked hours by team member (worked/expected):
Team Leader:
Paweł Gesek - 0.0/2.00
Przemysław Kornowski - 32.0/40.00
Developer:
Arkadiusz Lalo - 18.5/24.00
Daniel Serkowski - 0.0/24.00
Jakub Trzebiatowski - 18.0/24.00
Karol Cissewski - 17.0/24.00
What's done:
Ticket | Estimation(h) | Worked(h) | Total Worked(h) | Priority | Responsible |
---|---|---|---|---|---|
SYNCT-45: Add Rest Client Factory | 8.0 | 0.0 | 14.5 | TBD | Karol Cissewski |
FM-218: Create FHIR Strategy for Relationship object. | 8.0 | 1.0 | 18.5 | TBD | Jakub Trzebiatowski |
SYNCT-28: Create domain object for audit message | 24.0 | 6.5 | 6.5 | TBD | Przemysław Kornowski |
FM-240: Add FHIR client factory | 8.0 | 7.5 | 7.5 | TBD | Jakub Trzebiatowski |
SYNCT-52: Sync Persistence: Get local object method | 16.0 | 9.0 | 9.0 | TBD | Jakub Trzebiatowski |
Total | 64.0 | 24.0 | 56.0 |
What's in progress:
Ticket | Estimation(h) | Worked(h) | Total Worked(h) | Remaining(h) | Priority | Responsible |
---|---|---|---|---|---|---|
FM-212: Create FHIR Strategy for Form object. | 8.0 | 0.0 | 4.0 | 4.0 | TBD | Jakub Trzebiatowski |
FM-216: Create FHIR Strategy for PatientState object. | 8.0 | 0.0 | 3.0 | 5.0 | TBD | Jakub Trzebiatowski |
FM-207: Create FHIR Strategy for Encounter object. | 8.0 | 0.0 | 17.0 | 1.0 | TBD | Przemysław Kornowski |
FM-209: Create FHIR Strategy for Provider object. | 8.0 | 1.5 | 17.0 | 0.0 | TBD | Arkadiusz Lalo |
ATF-15: Create the atomFeed reader Factory | 8.0 | 3.0 | 3.0 | 5.0 | TBD | Jakub Trzebiatowski |
SYNCT-51: SyncClient: Push to the master | 24.0 | 16.0 | 16.0 | 8.0 | TBD | Karol Cissewski |
SYNCT-29: Add a logic for auditing. | 24.0 | 19.0 | 19.0 | 5.0 | TBD | Arkadiusz Lalo |
SYNCT-26: Add audit UI Grid | 24.0 | 22.0 | 22.0 | 2.0 | TBD | Przemysław Kornowski |
Total | 112.0 | 61.5 | 101.0 | 30.0 |
What's next:
Ticket | Estimation(h) | Worked(h) | Total Worked(h) | Remaining(h) | Priority |
---|---|---|---|---|---|
FM-210: Create FHIR Strategy for Allergy object. | 8.0 | 0.0 | 0.0 | 8.0 | TBD |
FM-204: Create FHIR Strategy for every object. | 0.0 | 0.0 | 0.0 | 0.0 | TBD |
FM-214: Create FHIR Strategy for Order object. | 12.0 | 0.0 | 0.0 | 12.0 | TBD |
FM-208: Create FHIR Strategy for Visit object. | 12.0 | 0.0 | 0.0 | 12.0 | TBD |
FM-215: Create FHIR Strategy for Patient Program object. | 8.0 | 0.0 | 0.0 | 8.0 | TBD |
FM-219: Create FHIR Strategy for Cohort object. | 8.0 | 0.0 | 0.0 | 8.0 | TBD |
SYNCT-27: Add audit details UI | 24.0 | 0.0 | 0.0 | 24.0 | TBD |
SYNCT-49: Move Hibernate Interceptor logic to the Event Module. | 24.0 | 0.0 | 0.0 | 24.0 | TBD |
Total | 96.0 | 0.0 | 0.0 | 96.0 |
Report for: 2017-11-28 - 2017-12-04
Sprint: Sync 2.0 Sprint 4, 2017-11-28 - 2017-12-12
Sprint goals:
Audit logic and UI. Start Push Workflow implementation.
Period value:
'%' closed tickets with high priority: 0% (0/0)
'%' closed tickets with medium priority: 24% (5/21)
'%' closed tickets with low priority: 0% (0/0)
'%' completed: 24% (5/21)
Hours:
Worked (Team Leader/Developer): 85.5 (32.0/53.5)
Remaining: 126.0
Worked hours by team member (worked/expected):
Team Leader:
Paweł Gesek - 0.0/2.00
Przemysław Kornowski - 32.0/40.00
Developer:
Arkadiusz Lalo - 18.5/24.00
Daniel Serkowski - 0.0/24.00
Jakub Trzebiatowski - 18.0/24.00
Karol Cissewski - 17.0/24.00
What's done:
Ticket | Estimation(h) | Worked(h) | Total Worked(h) | Priority | Responsible |
---|---|---|---|---|---|
SYNCT-45: Add Rest Client Factory | 8.0 | 0.0 | 14.5 | TBD | Karol Cissewski |
FM-218: Create FHIR Strategy for Relationship object. | 8.0 | 1.0 | 18.5 | TBD | Jakub Trzebiatowski |
SYNCT-28: Create domain object for audit message | 24.0 | 6.5 | 6.5 | TBD | Przemysław Kornowski |
FM-240: Add FHIR client factory | 8.0 | 7.5 | 7.5 | TBD | Jakub Trzebiatowski |
SYNCT-52: Sync Persistence: Get local object method | 16.0 | 9.0 | 9.0 | TBD | Jakub Trzebiatowski |
Total | 64.0 | 24.0 | 56.0 |
What's in progress:
Ticket | Estimation(h) | Worked(h) | Total Worked(h) | Remaining(h) | Priority | Responsible |
---|---|---|---|---|---|---|
FM-212: Create FHIR Strategy for Form object. | 8.0 | 0.0 | 4.0 | 4.0 | TBD | Jakub Trzebiatowski |
FM-216: Create FHIR Strategy for PatientState object. | 8.0 | 0.0 | 3.0 | 5.0 | TBD | Jakub Trzebiatowski |
FM-207: Create FHIR Strategy for Encounter object. | 8.0 | 0.0 | 17.0 | 1.0 | TBD | Przemysław Kornowski |
FM-209: Create FHIR Strategy for Provider object. | 8.0 | 1.5 | 17.0 | 0.0 | TBD | Arkadiusz Lalo |
ATF-15: Create the atomFeed reader Factory | 8.0 | 3.0 | 3.0 | 5.0 | TBD | Jakub Trzebiatowski |
SYNCT-51: SyncClient: Push to the master | 24.0 | 16.0 | 16.0 | 8.0 | TBD | Karol Cissewski |
SYNCT-29: Add a logic for auditing. | 24.0 | 19.0 | 19.0 | 5.0 | TBD | Arkadiusz Lalo |
SYNCT-26: Add audit UI Grid | 24.0 | 22.0 | 22.0 | 2.0 | TBD | Przemysław Kornowski |
Total | 112.0 | 61.5 | 101.0 | 30.0 |
What's next:
Ticket | Estimation(h) | Worked(h) | Total Worked(h) | Remaining(h) | Priority |
---|---|---|---|---|---|
FM-210: Create FHIR Strategy for Allergy object. | 8.0 | 0.0 | 0.0 | 8.0 | TBD |
FM-204: Create FHIR Strategy for every object. | 0.0 | 0.0 | 0.0 | 0.0 | TBD |
FM-214: Create FHIR Strategy for Order object. | 12.0 | 0.0 | 0.0 | 12.0 | TBD |
FM-208: Create FHIR Strategy for Visit object. | 12.0 | 0.0 | 0.0 | 12.0 | TBD |
FM-215: Create FHIR Strategy for Patient Program object. | 8.0 | 0.0 | 0.0 | 8.0 | TBD |
FM-219: Create FHIR Strategy for Cohort object. | 8.0 | 0.0 | 0.0 | 8.0 | TBD |
SYNCT-27: Add audit details UI | 24.0 | 0.0 | 0.0 | 24.0 | TBD |
SYNCT-49: Move Hibernate Interceptor logic to the Event Module. | 24.0 | 0.0 | 0.0 | 24.0 | TBD |
Total | 96.0 | 0.0 | 0.0 | 96.0 |
Report for: 2017-12-05 - 2017-12-12
Sprint: Sync 2.0 Sprint 4, 2017-11-28 - 2017-12-12
Sprint goals:
- Audit logic and UI.
- Start Push Workflow implementation.
Long-term goals:
Period value:
'%' closed tickets with high priority: 0% (0/0)
'%' closed tickets with medium priority: 42% (8/19)
'%' closed tickets with low priority: 0% (0/0)
'%' completed: 42% (8/19)
Hours:
Worked (Team Leader/Developer): 123.0 (49.0/74.0)
Remaining: 82.0
Worked hours by team member (worked/expected):
Team Leader:
Paweł Gesek - 1.0/2.40
Przemysław Kornowski - 48.0/48.00
Developer:
Arkadiusz Lalo - 9.0/28.80
Daniel Serkowski - 0.0/28.80
Jakub Trzebiatowski - 34.5/28.80
Karol Cissewski - 30.5/28.80
What’s done:
Ticket | Estimation(h) | Worked(h) | Total Worked(h) | Priority | Responsible |
---|---|---|---|---|---|
SYNCT-26: Add audit UI Grid | 24.0 | 8.0 | 30.0 | TBD | Przemysław Kornowski |
ATF-15: Create the atomFeed reader Factory | 8.0 | 0.0 | 3.0 | TBD | Jakub Trzebiatowski |
SYNCT-29: Add a logic for auditing. | 24.0 | 9.5 | 28.5 | TBD | Arkadiusz Lalo |
SYNCT-55: Audit logic tests and plugging into Sync services. | 12.0 | 10.0 | 10.0 | TBD | Arkadiusz Lalo |
SYNCT-54: SyncClient: Push to the Master through FHIR | 12.0 | 12.0 | 12.0 | TBD | Jakub Trzebiatowski |
SYNCT-56: Create PushService | 8.0 | 12.5 | 12.5 | TBD | Jakub Trzebiatowski |
SYNCT-51: SyncClient: Push to the master through REST | 24.0 | 32.5 | 48.5 | TBD | Karol Cissewski |
SYNCT-27: Add audit details UI | 24.0 | 24.5 | 24.5 | TBD | Przemysław Kornowski |
Total | 136.0 | 109.0 | 169.0 |
What's in progress:
Ticket | Estimation(h) | Worked(h) | Total Worked(h) | Remaining(h) | Priority | Responsible |
---|---|---|---|---|---|---|
FM-212: Create FHIR Strategy for Form object. | 8.0 | 0.0 | 4.0 | 4.0 | TBD | Jakub Trzebiatowski |
FM-216: Create FHIR Strategy for PatientState object. | 8.0 | 0.0 | 3.0 | 5.0 | TBD | Jakub Trzebiatowski |
FM-207: Create FHIR Strategy for Encounter object. | 8.0 | 0.0 | 17.0 | 1.0 | TBD | Przemysław Kornowski |
FM-209: Create FHIR Strategy for Provider object. | 8.0 | 0.0 | 17.0 | 0.0 | TBD | Arkadiusz Lalo |
Total | 32.0 | 0.0 | 41.0 | 10.0 |
What's next:
Ticket | Estimation(h) | Worked(h) | Total Worked(h) | Remaining(h) | Priority |
---|---|---|---|---|---|
FM-204: Create FHIR Strategy for every object. | 0.0 | 0.0 | 0.0 | 0.0 | TBD |
FM-214: Create FHIR Strategy for Order object. | 12.0 | 0.0 | 0.0 | 12.0 | TBD |
FM-208: Create FHIR Strategy for Visit object. | 12.0 | 0.0 | 0.0 | 12.0 | TBD |
FM-215: Create FHIR Strategy for Patient Program object. | 8.0 | 0.0 | 0.0 | 8.0 | TBD |
SYNCT-49: Move Hibernate Interceptor logic to the Event Module. | 24.0 | 0.0 | 0.0 | 24.0 | TBD |
FM-219: Create FHIR Strategy for Cohort object. | 8.0 | 0.0 | 0.0 | 8.0 | TBD |
FM-210: Create FHIR Strategy for Allergy object. | 8.0 | 0.0 | 0.0 | 8.0 | TBD |
Total | 72.0 | 0.0 | 0.0 | 72.0 |
Backlog:
Ticket | Estimation(h) | Worked(h) | Total Worked(h) | Remaining(h) | Status | Priority | Responsible |
---|---|---|---|---|---|---|---|
SYNCT-70: OpenMRS Sync 2.0 Retrospective & Planning | 6.0 | 6.0 | 6.0 | 0.0 | Closed | TBD | Przemysław Kornowski |
SYNCT-69: OpenMRS Sync 2.0 Sprint Review | 8.0 | 8.0 | 8.0 | 0.0 | In Progress | TBD | Jakub Trzebiatowski |
Total | 14.0 | 14.0 | 14.0 | 0.0 |
Report for: 2017-12-12 - 2017-12-18
Sprint: Sync 2.0 Sprint 5, 2017-12-12 - 2017-12-21
Sprint goals:
- Manual retry logic.
- Scheduler for Sync.
- Implement more objects in the Sync.
Period value:
'%' closed tickets with high priority: 0% (0/0)
'%' closed tickets with medium priority: 15% (2/13)
'%' closed tickets with low priority: 0% (0/0)
'%' completed: 15% (2/13)
Hours:
Worked (Team Leader/Developer): 87.0 (32.0/55.0)
Remaining: 112.5
Worked hours by team member (worked/expected):
Team Leader:
Paweł Gesek - 0.0/2.00
Przemysław Kornowski - 32.0/40.00
Developer:
Arkadiusz Lalo - 23.5/24.00
Daniel Serkowski - 25.0/24.00
Jakub Trzebiatowski - 6.5/24.00
Karol Cissewski - 0.0/24.00
Ticket | Estimation(h) | Worked(h) | Total Worked(h) | Priority | Responsible |
---|---|---|---|---|---|
SYNCT-71: Improve audit message details. | 16.0 | 19.0 | 19.0 | TBD | Daniel Serkowski |
SYNCT-30: The logic for retry messages | 8.0 | 24.5 | 24.5 | TBD | Arkadiusz Lalo |
Total | 24.0 | 43.5 | 43.5 |
What's in progress:
Ticket | Estimation(h) | Worked(h) | Total Worked(h) | Remaining(h) | Priority | Responsible |
---|---|---|---|---|---|---|
SYNCT-58: Person Object Pull & Push | 16.0 | 10.0 | 10.0 | 6.0 | TBD | Przemysław Kornowski |
SYNCT-60: Location Object Pull & Push | 16.0 | 6.5 | 6.5 | 9.5 | TBD | Jakub Trzebiatowski |
SYNCT-72: Improve details about failed push operation | 16.0 | 7.0 | 7.0 | 9.0 | TBD | Daniel Serkowski |
SYNCT-57: Scheduler for Pull & Push | 16.0 | 20.0 | 20.0 | 0.0 | TBD | Przemysław Kornowski |
Total | 64.0 | 43.5 | 43.5 | 24.5 |
What's next:
Ticket | Estimation(h) | Worked(h) | Total Worked(h) | Remaining(h) | Priority |
---|---|---|---|---|---|
SYNCT-62: Relationship Object Pull & Push | 16.0 | 0.0 | 0.0 | 16.0 | TBD |
SYNCT-68: Visit Type object Pull & Push | 12.0 | 0.0 | 0.0 | 12.0 | TBD |
SYNCT-64: Form Object Pull & Push | 12.0 | 0.0 | 0.0 | 12.0 | TBD |
SYNCT-65: Privilege Object Pull & Push | 12.0 | 0.0 | 0.0 | 12.0 | TBD |
SYNCT-66: Role object Pull & Push | 12.0 | 0.0 | 0.0 | 12.0 | TBD |
SYNCT-61: Program Object Pull & Push | 12.0 | 0.0 | 0.0 | 12.0 | TBD |
SYNCT-67: User object Pull & Push | 12.0 | 0.0 | 0.0 | 12.0 | TBD |
Total | 88.0 | 0.0 | 0.0 | 88.0 |
Backlog:
Ticket | Estimation(h) | Worked(h) | Total Worked(h) | Remaining(h) | Status | Priority | Responsible |
---|---|---|---|---|---|---|---|
SYNCT-70: OpenMRS Sync 2.0 Retrospective & Planning | 6.0 | 6.0 | 6.0 | 0.0 | Closed | TBD | Przemysław Kornowski |
SYNCT-69: OpenMRS Sync 2.0 Sprint Review | 8.0 | 8.0 | 8.0 | 0.0 | In Progress | TBD | Jakub Trzebiatowski |
Total | 14.0 | 14.0 | 14.0 | 0.0 |
@pkornowski It would be great to see more recent weekly reports.
Where could I get access to the updated reports for this project? could you share the link?
Regards Cynthia