Project Updates
Week 01: 2022-06-12T18:30:00Z→2022-06-18T18:30:00Z
- Got new mentors: @samuel34 (Primary Mentor), @dkibet (Secondary Mentor)
- Started Initialising the development environment project.
- Sent the first Pull request on initialising the project.
Week 02: 2022-06-19T18:30:00Z→2022-06-25T18:30:00Z
- Started working on the dashboard component.
- In my initial proposal, the design of the form builder was intended for the Ampath, but since it is for OpenMRS 3.x, the designs had to change. I created a few mockups and shared them with my mentors and the openmrs3 slack channel.
Dashboard Component
Form Builder and Form Viewer Components
Scheme Editor Component
@pauladams, It would be really helpful if you could provide some input on these designs.